Month 4

October 9, 2026

Construction continues to move forward on the State Route 41 Expressway Project, with crews making progress on earthwork, bridge preparation, drainage system improvements, and the future stormwater basins to accommodate drainage.

Crews have been removing soil from the southeast of Avenue 12/SR 41 intersection and relocating it to build up the new Avenue 11 Bridge overcrossing approaches. The north bridge abutment has reached its full height, with approximately 25 feet of fill placed, while work on the south abutment is nearing completion.

Earthwork is also progressing near the future stormwater basin. After preparing and leveling the area for the new roadway and basin, crews are beginning to excavate the basin to its final limits. Passersby may soon notice a pretty big hole out there. It’ll be hard to miss (and it’s not a swimming pool)! 

In preparation for continued construction near Avenue 11, crews recently restriped and shifted travel lanes along SR 41 and installed K-rail south of the existing bridge. The shift created additional space for crews to safely continue construction within the median and prepare for the upcoming traffic shift to accommodate bridge work.  Earthwork within the median is nearly complete.

Additional materials and equipment are also arriving on site for bridge construction. Floyd Johnston Construction Co continues to install drainage systems beneath what will be the future highway as part of Stage 1 of the project, with work progressing toward the larger and deeper drainage systems.

Construction activities will continue to increase as crews prepare for the next phase of bridge and roadway work.